REED BED CONSTRUCTION AT CHARNWOOD FOREST GOLF CLUB

BACKGROUND

An examination of the wash down water pad at CFGC showed that its retaining wall was broken in two places thus allowing potentially contaminated water to run to ground adjacent to the wash pad rather than entering the filtration system.

The filtration system was also rather old and overgrown indicating a lack of maintenance.

Further investigation revealed that the filtration system was not compliant with the latest legalisation The Environmental Permitting (England and Wales) Regulations 2010 which allows:-

The wash down of machinery taking place on a positively drained wash pad with all contaminated water removed and disposed of, fed into a mechanical water recycle system where it is cleaned, fed into a reed bed system or discharged into a foul sewer with full permission from the sewerage contractor.

REVIEW AND SELECTION

Two of these methods were selected for further investigation, the mechanical system and the reed bed.

Quotations were obtained for mechanical systems which were in the region of £27k.

A search for the design and construction of a reed bed varied from a design study alone costing £6k to a fully designed and installed system from Reed Bed Consultants costing in the region of £3.2k including all materials.

Needless to say the reed bed was chosen not only from the cost basis but also because of its natural way of treating the water and the nature of the available ground for construction. The existing filtration tanks were retained which act as a solids trap and the existing outlet pipe provided the feed to the bed.

The selected vertical reed bed works by using plants, gravel and microorganisms to naturally filter and clean dirty water. Water is gravity fed over the top of the reed bed and drains vertically down through the gravel. Air is pulled in as the water drains, creating an oxygen rich environment that excels at removing ammonia and organic matter. The treated water exiting the reed bed in this case flows to a soak away.

A 20sq meter reed bed was sufficient to treat the daily volume of water at CFGC and there is space to construct an additional bed if necessary.

CONSTRUCTION

Construction took a just over a day using golf club staff and equipment under the guidance of the consultant.

The reed bed took a few months to mature, care being taken to control weed growth and ensure it was not affected by wildlife.

The wash down pad retaining wall was replaced with kerbstones and an entry point rain strip was fitted to ensure rainwater doesn’t enter the wash down system.

For further information, please contact Gareth Cooper, Director of Sustainability at CFGC at garethtcooper@btinternet.com